In summary:- WP1 - Project Management
Task 1.1 Coordination between EU-BR consortia (co-leaders i2CAT and UFPA) Task 1.2 Quality Control EU (leader i2CAT) Task 1.3 Quality Control BR (leader UFPA) Task 1.4 Reporting EU (leader i2CAT) Task 1.5 Reporting BR (leader UFPA) Task 1.6 Financial Management and Cost Claims EU (leader i2CAT) Task 1.7 Collaboration tools (leader i2CAT)
- WP2 - Building and operating the Brazilian facility
T2.1 – Requirements analysis (M1-M3), leader: RNP T2.2 – Development of infrastructure/substrate (M4-M18), leader: UFPA T2.3 – Development of control and monitoring framework (M4-M30), leader: UFSCar T2.4 – Operation of the facilities (M04-M30), leader: RNP
- WP3 - Building and Operating the European Facility
T3.1 Detailed analysis of the new use cases and requirements specification (M1-M4), leader: i2CAT T3.2 Infrastructure update, (M1-M9), leader: University of Bristol T3.3 Enhancement to the OFELIA control framework (M5-M30), leader: i2CAT T3.4 Enhancement of the OMF control framework and the OML measurement framework (M5-M30), leader: UTH T3.5 Operation of the facility (M1-M30), leader: University of Bristol T3.6 Liaison with the FIBRE-BR testbed development (M1-M30), leader: RNP
- WP4 - Federation of facilities
T4.1: Analysis of the Federation requirements (M1-M12), leader: UPMC T4.2: Contribution to the Federation framework (M4-M24), leader: UFRJ T4.3: Federation Software Tools (M8-M30), leader: UNIFACS/UFPA T4.4: Federation Physical Interconnection (M12-M30), leader: RNP
- WP5 - Development of technology pilots and showcases
Task 5.1: Design and Development of Technology Pilots (M09-M18) - Leader: University of Bristol / CPqD Task 5.2: Preparation and Integration of local and federated showcases (M19 – M24) – Leader: University of Bristol / CPqD Task 5.3: Validation of local and federated facilities and showcases (M20 – M30) – Leader: University of Bristol / CPqD
- WP6 - Dissemination and Collaboration
Task 6.1 – Production and organization of dissemination material (M1-M30), leader: RNP/UTH Task 6.2 –Organization of workshops, tutorials and other events (M1-M30), leader RNP/UTH Task 6.3 – Collaboration (M1-M30), leader UFPA/UPMC


|